Hetch Hetchy Water and Power

Reservoir and Powerhouse Planned Releases

Period of June 8 - 21

 

Reservoir Releases*

Reservoir

Elevation (ft)

Storage (TAF)

Planned Releases (cfs)

Special Conditions

Hetch Hetchy

3805.3

358.9

500-1500

Hetchy Valve releases are at 920 cfs. After Hetch Hetchy fills, releases will follow inflows. Spill + Valve releases up to 1500 cfs is possible. Spill is expected to begin Monday, June 8.

Cherry

4685.9

244.1

5

None

Eleanor

4660.8

26.8

20-200

Eleanor may fill and begin to spill depending on inflows. Spill may reach up to 200 cfs.

 

Powerhouse Releases**

Powerhouse

Planned Tuolumne Releases (cfs)

Special Conditions

Kirkwood

500

Spill at KPH.

Holm

25

 

Moccasin***

100-200

Spill at Moccasin Reservoir

 

* Reservoir releases are dependent on storage and weather conditions, and can be changed at any time.

** Powerhouse releases can vary significantly dependent on power load and operational constraints. Planned releases are estimates.

*** Moccasin releases seen at Moccasin Creek between town of Moccasin and Don Pedro Reservoir. These releases do not affect Tuolumne River conditions, but do impact recreation in Moccasin Creek.