chris Site Admin
|
Posted: Apr 4, 2014Post Subject: Tuolumne - 2014 Release Predictions
|
|
| Hetch Hetchy Water and Power reports as follows:
"Hetch Hetchy Water and Power has begun our spring power generation program for reservoir management. We anticipate sending weekly updates of our operations every Wednesday or Thursday for the remainder of regular generation.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse. As always, unanticipated events may reduce or eliminate generation. All generation times will be at full capacity: 950 cfs from Holm PH. An additional 35 cfs is being released from Hetch Hetchy, 12 from Eleanor, and 5 from Cherry.
Fri | Apr 4 | 7AM to 4PM | 1000 cfs total
| Sat | Apr 5 | 7AM to 4PM | 1000 cfs total
| Sun | Apr 6 | 7AM to 4PM | 1000 cfs total
| Mon | Apr 7 | 7AM to 4PM | 1000 cfs total
| Tue | Apr 8 | 7AM to 4PM | 1000 cfs total
| Wed | Apr 9 | 7AM to 4PM | 1000 cfs total
| Thu | Apr 10 | 7AM to 4PM | 1000 cfs total
|
Note: There is scheduled maintenance April 15 at Holm Powerhouse - no extra generation is scheduled for this day. Expect 100-300 cfs in the Tuolumne.
Happy Boating"
|
chris Site Admin
|
| Yesterday, Hetch Hetchy Water and Power reported as follows:
"As of today, access is limited by the Forest Service due continuing effects of the Rim Fire. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) as well as the Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions:
http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
There is scheduled maintenance April 15 at Holm Powerhouse - no extra generation is scheduled for this day. Expect ~250 cfs in the Tuolumne.
Lake Eleanor is currently spilling at 220 cfs, and is expected to continue at this level tomorrow. To manage lake levels, HHWP will increase valve releases to 600 cfs on Saturday, April 12, for 6-10 hours. Ramping up and down will be between the hours of 9AM and 5PM. We expect Eleanor spill to drop after the increased release. Tuesday we will install the stop logs, which will further reduce spill.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse. As always, unanticipated events may reduce or eliminate generation. All generation times will be at full capacity: 950 cfs from Holm PH. An additional 35 cfs is being released from Hetch Hetchy, 12 from Eleanor, and 5 from Cherry.
Day | Date | Release Times | Holm PH Release
| Fri | Apr 11 | 7AM to 4PM | 950 cfs
| Sat | Apr 12 | 7AM to 4PM | 950 cfs
| Sun | Apr 13 | 7AM to 4PM | 950 cfs
| Mon | Apr 14 | 7AM to 4PM | 950 cfs
| Tue | Apr 15 | --- | No Release
| Wed | Apr 16 | 7AM to 4PM | 950 cfs
| Thu | Apr 17 | 7AM to 4PM | 950 cfs
|
The following are projected and estimated flows elsewhere in the drainage:
Day | Date | Eleanor Spill | MF SF Tuolumne | Approximate flow at Lumsden
| Fri | Apr 11 | 200 cfs | 175 cfs | 1350 cfs
| Sat | Apr 12 | 200 cfs | 175 cfs | 1350 cfs
| Sun | Apr 13 | 200-700 cfs | 150 cfs | 1800 cfs
| Mon | Apr 14 | 700-100 cfs | 150 cfs | 1500 cfs
| Tue | Apr 15 | 100 cfs | 150 cfs | 250 cfs
| Wed | Apr 16 | 50 cfs | 150 cfs | 1200 cfs
| Thu | Apr 17 | 50 cfs | 150 cfs | 1200 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"The Rim Dire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions:
http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
Beginning Thursday, April 24, we will begin 24 hour generation, which may run for most of the month of May. 24 hour generation is necessary for reservoir management and power generation concerns.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation. All generation times will be at full capacity: 950 cfs from Holm PH. An additional 35 cfs is being released from Hetch Hetchy, 20-200 from Eleanor (depending on spill patterns), and 5 from Cherry. Tuesday and Wednesday we will attempt to reduce spill from Eleanor to accommodate work on the Lower Cherry Aqueduct.
| Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | Apr 18 | Apr 19 | Apr 20 | Apr 21 | Apr 22 | Apr 23 | Apr 24
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | 7AM - 4PM | 7AM - 4PM | All day | 7AM - 4PM | 7AM - 4PM | 7AM - 4PM | All day
| Eleanor Spill | 20-200 cfs | 20-200 cfs | 20-200 cfs | 20-200 cfs | 20-50 cfs | 20-50 cfs | 20-200 cfs
| MF SF Tuolumne | 150 cfs | 150 cfs | 150 cfs | 150 cfs | 150 cfs | 150 cfs | 150 cfs
| Approx Merals Pool flow | 1300 cfs | 1300 cfs | 1300 cfs | 1200 cfs | 1200 cfs | 1300 cfs | 1300 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions:
http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
Beginning Thursday, April 24, we will begin 24 hour generation, which may run for most of the month of May. 24 hour generation is necessary for reservoir management and power generation concerns.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity: 950 cfs from Holm PH. An additional 35 cfs is being released from Hetch Hetchy, 20-100 from Eleanor (depending on spill patterns), and 5 from Cherry.
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | Apr 24 | Apr 25 | Apr 26 | Apr 27 | Apr 28 | Apr 29 | Apr 30 | May 1
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | All day | All day | All day | All day | All day | All day | All day | All day
| Eleanor Spill | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20-100 cfs | 20-100 cfs | 20-100 cfs
| MF SF Tuolumne | 120 cfs | 120 cfs | 120 cfs | 120 cfs | 120 cfs | 120 cfs | 120 cfs | 120 cfs
| Approx Merals Pool flow | 1100 cfs | 1100 cfs | 1100 cfs | 1100 cfs | 1100 cfs | 1100 cfs | 1100 cfs | 1100 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions:
http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79 [www.fs.usda.gov]
We are continuing 24 hour generation, which may run for most of the month of May. 24 hour generation is necessary for reservoir management and power generation concerns.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 35 cfs is being released from Hetch Hetchy and 5 cfs from Cherry Lake. Eleanor is spilling, and we expect spill rates to be around 100-200 cfs through next week.
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | May 1 | May 2 | May 3 | May 4 | May 5 | May 6 | May 7 | May 8
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | All day | All day | All day | All day | All day | All day | All day | All day
| Eleanor Spill | 200 cfs | 200 cfs | 100-200 cfs | 100-200 cfs | 100-200 cfs | 100-200 cfs | 100-200 cfs | 100-200 cfs
| MF SF Tuolumne | 200 cfs | 150-250 cfs | 150-250 cfs | 150-250 cfs | 150-250 cfs | 150-250 cfs | 150-250 cfs | 150-250 cfs
| Approx Merals Pool flow | 1500 cfs | 1400-1600 cfs | 1400-1600 cfs | 1400-1600 cfs | 1400-1600 cfs | 1400-1600 cfs | 1400-1600 cfs | 1400-1600 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"Hetch Hetchy Water and Power has released the summer release schedule, posted here: http://www.dreamflows.com/Pages/TuolumneSchedule.php
The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions: http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
We are continuing 24 hour generation, which could run for most of the month of May. 24 hour generation is necessary for reservoir management and power generation concerns.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 80 cfs is being released from Hetch Hetchy, 25 cfs from Eleanor and 5 cfs from Cherry Lake. Eleanor has stopped spilling, but is expected to begin again later this week. Spill volumes are expected to peak at less than 200 cfs."
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | May 8 | May 9 | May 10 | May 11 | May 12 | May 13 | May 14 | May 15
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | All day | All day | All day | All day | All day | All day | All day | All day
| Eleanor Spill | 25 cfs | 25 cfs | 25-50 cfs | 25-100 cfs | 25-200 cfs | 25-200 cfs | 25-200 cfs | 25-200 cfs
| MF SF Tuolumne | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs
| Approx Merals Pool flow | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs
|
Happy Boating"
|
Studytime Member
|
| How is this weekend looking?
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"Hetch Hetchy Water and Power has released the summer release schedule (posted at http://www.dreamflows.com/Pages/TuolumneSchedule.php). This schedule describes planned releases at Holm Powerhouse for end of May, June, July and August. Powerhouse outages and other unanticipated events may result in curtailments of releases. Additional generation may occur throughout this period, likely extending boatable hours, or increasing in stream flow rates. Releases for May, and extension of boatable hours through the summer will be described in this and future emails.
The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions: http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
We are continuing 24 hour generation, which could run for most of the month of May. 24 hour generation is necessary for reservoir management and power generation concerns.
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 80 cfs is being released from Hetch Hetchy, 20 cfs from Eleanor and 5 cfs from Cherry Lake. Eleanor has stopped spilling, and it is unknown whether it will spill again this season."
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | May 15 | May 16 | May 17 | May 18 | May 19 | May 20 | May 21 | May 22
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | All day | All day | All day | All day | All day | All day | All day | All day
| Eleanor Spill | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs
| MF SF Tuolumne | 100 cfs | 75-125 cfs | 75-125 cfs | 75-125 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs | 50-150 cfs
| Approx Merals Pool flow | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs
|
Happy Boating"
|
Studytime Member
|
Posted: May 21, 2014Post Subject: How long will releases last?
|
|
| I couldn't find anywhere where it said how long release will go for. I thought I red only till June 10th but that doesn't sound right. Anybody have any date?
|
chris Site Admin
|
| The schedule page gives official recreational release details.
|
chris Site Admin
|
| Hetch Hetchy Water and Power reported yesterday (Wednesday) as follows:
"We are ending 24 hour generation today, May 21. Thursday and Friday, and Tuesday through Friday next week we are generating between 7AM and 11PM. Over the coming long weekend we will go back to 24 hour generation. We anticipate varied boatable hours from now until June 16, as we maximize generation efficiency. During this period, we will extend generation for variable durations to either side of the recreational flows. Starting June 16, we are planning on limiting generation to the recreational flows (7AM - 11AM).
Hetch Hetchy Water and Power has released the summer release schedule (posted at http://www.dreamflows.com/Pages/TuolumneSchedule.php. This schedule describes planned releases at Holm Powerhouse for end of May, June, July and August. Note that June 11 is the first no water Wednesday of the season. There will be no boatable flows that day. Powerhouse outages and other unanticipated events may result in curtailments of releases. Additional generation may occur throughout this period, likely extending boatable hours, or increasing in stream flow rates. Releases for May, and extension of boatable hours through the summer will be described in this and future emails.
The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions: http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 80 cfs is being released from Hetch Hetchy, 20 cfs from Eleanor and 5 cfs from Cherry Lake. Eleanor has stopped spilling, and it is unknown whether it will spill again this season. "
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | May 22 | May 23 | May 24 | May 25 | May 26 | May 27 | May 28 | May 29
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | 7AM to 11PM | 7AM to 11PM | All day | All day | All day | 7AM to 11PM | 7AM to 11PM | 7AM to 11PM
| Eleanor Spill | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs
| MF SF Tuolumne | 80 cfs | 50-100 cfs | 50-100 cfs | 50-100 cfs | 50-100 cfs | 50-100 cfs | 50-100 cfs | 50-100 cfs
| Approx Merals Pool flow | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs | 1150-1250 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"As runoff comes to a close and generation needs are filled, HHWP is reducing generation. This week we are generating 15 hours per day during the week, and 4 hours over the weekend (see table below). Starting June 16, we are planning on limiting generation to the recreational flows (7AM - 11AM).
Hetch Hetchy Water and Power has released the summer release schedule (posted at http://www.dreamflows.com/Pages/TuolumneSchedule.php). This schedule describes planned releases at Holm Powerhouse for end of May, June, July and August. Note that June 11 is the first no water Wednesday of the season. There will be no boatable flows that day. Powerhouse outages and other unanticipated events may result in curtailments of releases. Additional generation may occur throughout this period, likely extending boatable hours, or increasing in stream flow rates. Releases for May, and extension of boatable hours through the summer will be described in this and future emails.
The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions: http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 80 cfs is being released from Hetch Hetchy, 20 cfs from Eleanor and 5 cfs from Cherry Lake. Eleanor has stopped spilling, and it is unknown whether it will spill again this season."
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | May 29 | May 30 | May 31 | Jun 1 | Jun 2 | Jun 3 | Jun 4 | Jun 5
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs
| Holm PH Release Times | 7AM to 10PM | 7AM to 10PM | 7AM to 11AM | 7AM to 11AM | 7AM to 10PM | 7AM to 10PM | 7AM to 10PM | 7AM to 10PM
| Eleanor Spill | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs | 20 cfs
| MF SF Tuolumne | 40-80 cfs | 40-80 cfs | 40-80 cfs | 40-80 cfs | 40-80 cfs | 40-80 cfs | 40-80 cfs | 40-80 cfs
| Approx Merals Pool flow | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs | 1100-1200 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"Note that June 11 is the first no water Wednesday of the season. There will be no boatable flows that day. Over the weekend we will just release recreational flows. We anticipate this being the last week with more than recreational flows during the week.
Hetch Hetchy Water and Power has released the summer release schedule (posted at http://www.dreamflows.com/Pages/TuolumneSchedule.php). This schedule describes planned releases at Holm Powerhouse for end of May, June, July and August. Powerhouse outages and other unanticipated events may result in curtailments of releases. Additional generation may occur throughout this period, likely extending boatable hours, or increasing in stream flow rates. Releases for May, and extension of boatable hours through the summer will be described in this and future emails.
The Rim Fire Closure has been revised by the Forest Service. Public access to the Main Tuolumne/Merals Pool launch on Lumsden Road (1N10) is now open. The Upper Tuolumne/Cherry Creek launch at Holm Powerhouse off of Cherry Lake Road (1N07) is limited to shuttle service only: 1-209-559-4605. A permit is required to float between Cherry Creek and Merals Pool and from Merals Pool to Ward's Ferry. Free permits can be picked up at the Groveland Ranger Station during business hours. The following link has additional details on the restrictions: http://www.fs.usda.gov/recarea/stanislaus/recreation/wateractivities/recarea/?recid=14975&actid=79
The table below shows the days and times HHWP is scheduled to generate at Holm Powerhouse, and estimates of flows from Eleanor and the Middle Fork and South Fork of the Tuolumne. As always, unanticipated events may reduce or eliminate generation, or increase spill at Eleanor. All generation times will be at full capacity - 950 cfs from Holm PH. An additional 75 cfs is being released from Hetch Hetchy, 20 cfs from Eleanor and 5 cfs from Cherry Lake.
| Thu | Fri | Sat | Sun | Mon | Tue | Wed | Thu
| | Jun 5 | Jun 6 | Jun 7 | Jun 8 | Jun 9 | Jun 10 | Jun 11 | Jun 12
| Release Holm PH | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | 950 cfs | No Gen | 950 cfs
| Holm PH Release Times | 7AM to 10PM | 7AM to 10PM | 7AM to 11AM | 7AM to 11AM | 7AM to 10PM | 7AM to 10PM | No Gen | 7AM to 10PM
| Eleanor Spill and MF SF Tuolumne etc | 100-150 cfs | 100-150 cfs | 100-150 cfs | 100-150 cfs | 100-150 cfs | 100-150 cfs | 100-150 cfs | 100-150 cfs
| Approx Merals Pool flow | 1050-1150 cfs | 1050-1150 cfs | 1050-1150 cfs | 1050-1150 cfs | 1050-1150 cfs | 1050-1150 cfs | 100-150 cfs | 1050-1150 cfs
|
Happy Boating"
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"Only 'normal' boating hours will be scheduled beginning Tuesday June 17th. So this is the last update for the season. The schedule is posted at http://www.dreamflows.com/Pages/TuolumneSchedule.php for your reference. Have a nice summer."
|
chris Site Admin
|
| Hetch Hetchy Water and Power reports as follows:
"Rafting People!
One unit at Holm Powerhouse went down this morning at 7AM. We are sending people up to fix the problem, but do not expect a solution for at least 2 hours. Rafting flows may not occur at all today, depending on how the repairs go. We will generate full with one unit, and expect flows to stay at 550 cfs in Cherry Creek, and 625 cfs in the Tuolumne River.
We do not anticipate this problem extending to tomorrow, but will let you know as the repairs progress."
| | |